Updated on 2025-08-08 GMT+08:00

Viewing the Change Calendar

Scenarios

After a change ticket is created, you can view the distribution and details of the change ticket in the change calendar by month or day. The detailed operations are as follows:

Viewing the Change Calendar

  1. Log in to COC.
  2. In the navigation pane on the left, choose Change Ticket Mgmt > Change Calendar.

    • By default, the distribution of changes reviewed in the current month is displayed. You can click a change title to go to the corresponding change ticket details page.
    • You can filter changes by change application, change level, status, and change title.
    • To view the change information of a day, click the corresponding date.
    • Change tickets in the Pending review, Pending implementation verification, Successful, Failed, and Canceled states are displayed in the change calendar.
    • By default, the change application and title are displayed in the change calendar. Different colors indicate different change status.
    • Rules for sorting change tickets:
      • The sorting based on the cross-day duration is used preferentially, with longer cross-day duration yielding higher ranking
      • The change plan with an earlier start time ranks higher.
      • If the change plans start at the same time, the one created first ranks higher.