文档首页/ 数据复制服务 DRS/ 故障排除/ 失败案例/ MySQL->MySQL实时迁移和同步/ 全量阶段失败报错,关键词“ caused by: shard table=*** failed. message is Communications link failure”
更新时间:2026-11-05 GMT+08:00
分享

全量阶段失败报错,关键词“ caused by: shard table=*** failed. message is Communications link failure”

场景描述

全量迁移或编辑任务DRS任务报错,日志提示信息:An error occurred in the process DATAMOVE, caused by: shard table=*** failed. message is Communications link failure The last packet successfully received from the server was *** milliseconds ago或child transfer failed,An error occurred in the process child_full, caused by: shard table=*** failed. message is Communications link failure The last packet successfully received from the server was *** milliseconds ago

可能原因

源库性能不足或网络不稳定导致源库数据分片超时。

解决方案

  1. 查看任务状态是否正常。

    • 任务状态正常,该报错为日志中显示,无需处理。
    • 任务状态异常,执行步骤2。

  2. 参考修改任务参数,按照不同链路调大超时参数“datamove_source_socket_timeout“,参数修改后续传任务。