Updated on 2024-10-29 GMT+08:00

Creating an Application

You can create an application to facilitate resource management by service logic unit.

Scenarios

Create an application on COC.

Precautions

An application cannot contain both sub-applications and components.

Procedure

  1. Log in to COC.
  2. In the navigation pane, choose Resources > Application and Resource Management. On the displayed page, click the Applications tab and click Create Application.

    Figure 1 Creating an application

  3. On the Create Application page, configure required information and click Submit. For details, see Table 1.

    Figure 2 Setting parameters
    Table 1 Parameters for creating an application

    Parameter

    Description

    Example Value

    Application ID

    (Mandatory) In the Basic Information area, enter an application ID.

    testApplication

    Application

    (Mandatory) In the Basic Information area, enter the application name.

    Test Application

    Enterprise Project

    (Mandatory) In the Basic Information area, specify the enterprise project, which the application belongs to.

    default

    Description

    (Optional) In the Basic Information area, provide important information about the application.

    -

    Component ID

    (Mandatory) In the Application Configuration area, enter the ID of the component you want to create.

    testComponent

    Component

    (Mandatory) In the Application Configuration area, enter the name of the component you want to create.

    Test Component

    Group ID

    (Mandatory) Group of the component you created. Enter a valid group ID.

    testGroup

    Group

    (Mandatory) Group of the component you created. Enter a valid group name.

    Test Group

    Resource Association Method

    (Mandatory) Method that is used to associate resources with the group you created. There are two association methods: manual association and intelligent association.

    • Manual: You can manually associate resources with the group you created for unified management.
    • Intelligent: You can add all resources with the same tag in an enterprise project to a resource group.

    Manual

    Tag Key

    (Mandatory) This parameter is displayed if the intelligent resource association method is used.

    testKey

    Tag Value

    (Optional) This parameter is displayed if the intelligent resource association method is used.

    testValue