Updated on 2023-10-24 GMT+08:00

Resuming a Stopped Project

Prerequisites

  • Project Status of an evaluation project is Stopped.
  • Frozen accounts cannot resume a stopped project.

Procedure

  1. Log in to the UGO console.
  2. In the navigation pane on the left, choose Schema Migration > DB Evaluation.
  3. In the evaluation project list, locate the project whose Project Status is Stopped and click Resume in the Operation column.

    Figure 1 Resuming an evaluation task

  4. To use the current settings, click OK.
  5. (Optional) To modify the current settings, click Edit. Then, configure DB Connection Timeout and Data Collection, and click OK.

    Figure 2 Editing settings
    • DB Connection Timeout: specifies the time limit within which the system attempts to connect to the database, in millisecond. Value: 30000 to 1800000.
    • Skip Collection Timeout Object
      • Select this option: If the database connection times out, the system skips some objects and records the objects that failed to be collected, and continues to create an evaluation project.
      • Deselect this option: If the database connection times out, the evaluation project creation will be stopped. You need to change the database connection timeout and resume the creation of the project.