Help Center> CodeArts Req> User Guide> IPD-System Device Projects> Tasks> Introduction to Status Transition
Updated on 2024-05-21 GMT+08:00

Introduction to Status Transition

The entire life cycle of a task consists of the Initial, Processing, and Completed states. Figure 1 shows the complete status transition process.

Figure 1 Task status transition flowchart

Table 1 describes operations in each state.

Table 1 Operation description

State

Description

Operation

Initial

When a task is created, the state is Initial by default.

  1. Creating Tasks
  2. Editing a Task in the Initial State

Processing

After the task in the Initial state is processed, the state changes to Processing.

Editing a Task in the Processing State

Completed

After the task is processed, the state changes to Completed.

N/A