Cluster Overload Control

Scenario

If enabled, concurrent requests are dynamically controlled based on the resource pressure of master nodes to keep them and the cluster available.

Constraints

The cluster version must be 1.23 or later.

Enabling Overload Control

Method 1: Enabling it when creating a cluster

When creating a cluster of v1.23 or later, you can enable overload control during the cluster creation.

Figure 1 Enabling overload control during cluster creation

Method 2: Enabling it in an existing cluster

  1. Log in to the CCE console and click the name of an existing cluster whose version is v1.23 or later.
  2. On the Overview page, check the master node information. If overload control is not enabled, a message will be displayed. You can click Enable to enable the function.

    Figure 2 Enabling overload control for an existing cluster

Disabling Cluster Overload Control

  1. Log in to the CCE console and go to an existing cluster whose version is v1.23 or later.
  2. In the navigation pane, choose Settings.
  3. On the Cluster Access tab page, disable overload control.
  4. Click OK.