Solution Design
Deployment Plan
To deploy the system on HUAWEI CLOUD, keep the application architecture unchanged and replace third-party cloud services with HUAWEI CLOUD services.
For details about the deployment solution design, refer to section Deployment Plan.
Networking Plan
The system networking on HUAWEI CLOUD is the same as that of the source end. The system connects to a third-party cloud through EIP and VPN or Direct Connect.
For details, see Networking Plan.
Security Design
- For details, see Security Design. Find more information in the SAP Security White Paper.
- For details about permission management, see Service Account System Design.
Migration Plan
Table 1 lists the recommended migration solutions.
Object |
Solution |
Description |
---|---|---|
Application servers |
Server Migration Service
NOTE:
The source server must access HUAWEI CLOUD SMS. Bind a public IP address to the source server. |
SMS supports online and incremental migration. You can migrate SAP application servers while the applications are running, and synchronize incremental data several times. Data transmission time = Actual data volume/Actual network bandwidth Table 2 lists the estimated time for transmitting 1 TB data. Estimate the time required for transmitting data based on the actual data volume. If the data cannot be transmitted within the estimated time, increase the network bandwidth. |
Database |
|
When using SMS, you need to stop the database servcie before the migration to ensure data consistency. The service interruption duration of using native database tool is shorter than that of using the SMS. For details about the estimated interruption duration, see section Table 1. |
Network Bandwidth |
2 Mbit/s |
10 Mbit/s |
50 Mbit/s |
100 Mbit/s |
---|---|---|---|---|
Theoretical time (80% network utilization rate)
NOTE:
Transmission time (days) = [Total capacity (KB)]/[Bandwidth (Mbit/s) x 125 x Network utilization rate x 60 (seconds) x 60 (minutes) x 24 (hours)] |
106 days |
13 days |
60 hours |
30 hours |
Service Switchover Plan
The owner of the service switchover plan is the migration implementor. This section provides an example of the service switchover plan.
Migration Solution |
Switchover Plan |
Impact |
---|---|---|
The application servers are redeployed on or migrated to HUAWEI CLOUD by importing images. The database is restored using backup data. |
|
The service interruption duration = the incremental backup duration + the incremental backup transmission duration + the incremental data restoration duration |
Use SMS to migrate the application servers, and the database replication function to synchronize database. |
|
Stop source end services only after the last incremental synchronization is performed using SMS. After the cloud database takes over the services, the service switchover is complete. The service interruption duration is the database switchover duration. |
Feedback
Was this page helpful?
Provide feedbackThank you very much for your feedback. We will continue working to improve the documentation.See the reply and handling status in My Cloud VOC.
For any further questions, feel free to contact us through the chatbot.
Chatbot