Edit work item | On the R&D requirement details page, click the value box of the field to be modified, and enter a target value in the text box or select one from the drop-down list. The modification is saved automatically. | You must have permission to edit R&D requirements. |
Change work item status | Go to the work item details page, click the Status field, and transition the work item to the target status. For details about status transition, see Table 1. | You must have permission to set statuses for R&D requirements. |
Baseline R&D requirement | - Go to the work item details page, and choose
> Baseline. The Baseline dialog box is displayed. - Click OK.
The baseline icon is displayed on the left of the R&D requirement title. You can unbaseline R&D requirements that have been baselined.
| You must have permission to baseline R&D requirements. |
Initiate baseline review | - Go to the work item details page, and choose
> Baseline Review. The BR page is displayed. - Enter BR information.
By default, the Baseline Object is the R&D requirement for which the baseline review is initiated. - Click Submit. The Review page is displayed.
Choose Review > Baseline Review to check the new baseline review. - Switch to the R&D Requirements page. The icon of the R&D requirement that is under baseline review is displayed as
. Track the progress of the baseline review. The R&D requirement can be baselined only when the baseline review status changes to Approved.
| You must have permission to view R&D requirements. |
Initiate change review | The change process can be initiated only for baselined and uncompleted R&D requirements. - Go to the details page of a baselined work item, and choose
> Change Review. The CR page is displayed. - Enter CR information.
- Change Object: By default, it is the R&D requirement to be changed.
- Collaborative Parent Item Change: Only existing CRs can be added.
- Click Submit. The Review page is displayed.
Choose Review > Change Review to check the new CR in the change process. The CR state is Pending review by default. Track the progress of the CR. Only when the state is Approved, which means that the CR has been processed, will the changed content display in the corresponding R&D requirement.
| You must have permission to view R&D requirements. |
Upload attachment | Attachments can be pictures, workbooks, manuscripts, and text files. A maximum of 100 attachments can be added to each work item, and their total size cannot exceed 500 MB. - Go to the work item details page, and click the Attachment tab.
- Click the box to select a local file or drag the file here to upload it as an attachment for the work item.
Local files can be directly dragged to the text box. When the upload progress reaches 100%, the system displays a message indicating that the attachment is uploaded successfully. Move the cursor to the file that is successfully uploaded. The operations that can be performed are displayed. - Click
to download the file. - Click
to delete the uploaded file.
| You must have permission to edit or upload attachments for R&D requirements. |
Add and check related item | A work item can be associated with other types of work items in a project. - Go to the work item details page and click the Related Items tab.
- Complete association.
- Parent Work Items Related to IR: parent requirement to which an R&D requirement belongs.
The information about an RR is displayed in the Parent Requirements area only when the IR is associated with the RR. - Parent Features: parent feature to which an R&D requirement belongs.
Only when an IR is associated with a feature will the information about the feature be displayed in the Parent Features area. - Subrequirement: SRs of a child requirement in the current R&D requirement.
A maximum of 10 child requirements can be created at a time. One child requirement is displayed by default and cannot be deleted. 1. Click Break Down. The Break Down Subrequirements window is displayed. 2. Configure a child requirement. Click to expand and configure more information. 3. Click OK. The child requirement is automatically displayed under the parent requirement in the R&D requirement list. - Related Upstream Requirements: requirements assigned by other projects to your project.
- Related Downstream Requirements: requirements assigned to downstream projects.
For details, see Assigning Requirements and Operations Related to Requirement Assignment. - Associate Work Item: associated work items of other types in the project. Work items of the RR, SF, IR, SR, AR, task, and bug types can be associated.
- Associated open issue review form: reviews that include the review and approval comments related to the work item.
- Test Case: test cases corresponding to the R&D requirement. You can select R&D requirements associated with test cases in CodeArts TestPlan.
- Code Commit Record: indicates the code commit records corresponding to the R&D requirement.
Related information is displayed only when the current requirement is associated during code commit. - Code Branch: code branches corresponding to the R&D requirement.
Related information is displayed only when a code branch is associated with the current requirement. - Code Merge & Change Request: code merge and change requests corresponding to an R&D requirement.
Related information is displayed only when a submitted merge or change request is associated with the current requirement.
| You must have permission to deliver/cancel assignment, create/delete child requirements, associate/dissociate work items, associate/dissociate files, and associate/dissociate wikis for R&D requirements. |
Check review record | You can check the review records related to requirements only in the following situations: - When an R&D requirement is added to a baseline review, the baseline review process is triggered. Only then will you be able to view the review record on the Review tab of the corresponding R&D requirement details page.
- When a locked field of a baselined R&D requirement is modified, the change process is automatically triggered. Only then will you be able to view the review record on the Review tab of the corresponding R&D requirement details page.
- When an R&D requirement has a general review record, you can check the record on the Review tab of the R&D requirement details page.
| You must have permission to view R&D requirements. |
Add workload | - Go to the work item details page and click the Workload tab.
- Click Add Workload. The Add Workload dialog box is displayed.
- Enter the workload information.
- The end date cannot be earlier than the start date.
- Decide whether to select Weekends included. If not, weekend workload records will not be generated.
- You can select Total or Daily for Workload.
- Work Type options include backend development, frontend development, UI design, replacement leave, debugging, and general. You can also customize the value by referring to Creating Work Types.
- Click OK.
The system automatically generates corresponding records based on the entered dates and days. The workload can be edited and deleted.
| You must have permission to add person-hours for R&D requirements. Workloads can be edited and deleted by the creator. By default, the project administrator can edit and delete all workloads. |
View operation history | History displays all operation logs of users, including creation, status transition, review initiation, work item association, and workload addition. - Go to the work item details page.
- Click the History tab.
- Click
or to check historical records in the ascending or descending order of operation time. - You can set search criteria to query historical records that meet the search criteria.
| You must have permission to view R&D requirements. |
Tag work item | - Go to the work item details page. Click
next to Tag at the top of the page, and select Create Tag. The added tag is displayed in the Tag area. - In the Create Tag dialog box, set Tag Name and select Tag Color.
- Click OK.
The new tag is displayed next to the requirement ID in the R&D requirement list. - (Optional) Hide a tag.
| You must have permission to edit R&D requirements. |
Add comment | - Go to the work item details page.
- On the Details tab page, click the Comments text box.
Figure 4 Add comment - Enter a comment.
You can upload images, enter links, associate work items, and use @ to notify project members in comments. - Click Submit.
Submitted comments can be replied, edited, pinned to the top, and deleted.
| You must have permission to view R&D requirements. |