| Edit work item | On the work item details page, click the value box of the field to be modified, and enter a target value in the text box or select one from the drop-down list. The changes are saved automatically. | You must have permission to edit custom work items. |
| Change work item status | Go to the work item details page, click the Status field, and transition the work item to the target status. | You must have permission to set statuses for custom work items. |
| Baseline work item | - Go to the work item details page, and choose
> Baseline. The Baseline dialog box is displayed. - Click OK.
You can see the baseline icon on the left of the work item title. For example, is displayed for a based SG. You can unbaseline work items that have been baselined. | You must have permission to baseline custom work items. |
| Change work item | The change process can be initiated only for baselined and uncompleted work items. - Go to the details page of a baselined work item, and choose
> Change Review. The CR page is displayed. - Enter CR information.
- Enter basic information, including Description, Start, End, and Copy To.
- Set change objects: Click Add in the Change Objects area. In the displayed dialog box, select the work item types to be changed from the drop-down list and click Add.
- Set associated files: If there are associated files, upload them on the Attachments tab of the Associated Files area.
- Collaborative Parent Item Change: CRs can be added only when they already exist in the system.
- Click Submit. The Review page is displayed.
Choose to view the new CR in the change process. The CR state is Pending review by default. Track the approval progress of the CR. Only when the state is END, which means that the CR has been processed, will the changed content be displayed in the corresponding list of a custom function page. | You must have permission to check custom work items. |
| Upload attachment | Attachments can be pictures, workbooks, manuscripts, and text files. A maximum of 100 attachments can be added to each work item, and their total size cannot exceed 500 MB. - Go to the work item details page, and click the Attachment tab.
- Click Click or drag the file here to upload it., select a local file, and upload the file to the work item as an attachment.
Local files can be directly dragged to the text box. When the upload progress reaches 100%, the system displays a message indicating that the attachment is uploaded successfully. Move the cursor to the uploaded file. The available operations are displayed. - Click
to download the file. - Click
to delete the uploaded file. | You must have permission to edit or upload attachments for custom work items. |
| Add and check associated item | A work item can be associated with other types of work items in a project. - Go to the work item details page and click the Related Items tab.
- Complete association.
- Parent work item: Parent work item that the work item is subordinated to.
The parent work item area displays information about the parent work item only when the work item has a parent work item. You can associate a work item with its parent work item only when the work item is the top-level work item on the current function page and is a child work item of another work item type. For details about the concepts of the work item hierarchy tree, see Table 2. - Child work item: Child work items broken down from the current work item.
Each work item can be broken down into a maximum of 10 child work items at a time. One child requirement is displayed by default and cannot be deleted. 1. Click Break Down. The Break Down Child Work Item dialog box is displayed. 2. Configure the child work item information. Click to expand and configure more information. 3. Click OK. The child work item is automatically displayed under the parent work item in the list of a custom function page. - Related Upstream Work Items: work items assigned by other projects to your project.
- Related Downstream Work Items: work items assigned to downstream projects.
- Associate Work Item: associated work items of any other types in the project. All work item types configured in Configuring Work Item Type Templates can be associated.
- Custom work item associations. The name displayed is the same as the name of the work item association configured in Configuring Work Item Associations. The work item types that can be associated are the intersection of those configured in Configuring Work Item Associations and those supported by the current project.
- Files: Files corresponding to the current work item.
Select a file associated with the current work item. You can upload a local file. - Wiki: wikis corresponding to the current work item.
Select a wiki associated with the current work item. You can also create a wiki. - Test Case: test cases related to the current work item. You can select a test case associated with the work item in CodeArts TestPlan.
- Test Design: test design related to the current work item. You can select the test design associated with the work item in CodeArts TestPlan.
- Test Plan: test plans related to the current work item. You can select a test plan associated with the work item in CodeArts TestPlan.
- Code Commit Record: code commit records related to the current work item.
Related information is displayed only when the current work item ID is associated with a code commit. - Code Branch: code branch corresponding to the current work item.
Related information is displayed only when a code branch is associated with the current work item. - Code Merge & Change Request: code merge and change requests corresponding to the current work item.
Related information is displayed only when a submitted merge or change request is associated with the current work item. - External Link: external links associated with the current work item.
- Create link: Click Add Link. In the displayed dialog box, set Link Name and Link. The value of Link must start with https:// and cannot contain invalid characters, such as spaces and Chinese characters. Click OK.
After a link is created, you can click External Link to view, edit, copy, or delete the link. 
- Copy link: Click
on the right of the link to be copied. - Edit link: Click
on the right of the link to be edited. In the Edit Link dialog box, you can change the Link Name and Link. - Delete link: Click
on the right of the link to be deleted. In the displayed dialog box, click Delete. | You must have the permissions to assign or cancel assignment of, break down, associate or dissociate, and associate or dissociate a parent work item for custom work items. |
| View review records | You can check the review records of the work item only in the following situations: - When a work item is added to a baseline review, the baseline review process is triggered. Only then will you be able to view the review record on the Review tab of the corresponding work item details page.
- When a locked field of a baselined work item is modified, the change process is automatically triggered. Only then will you be able to view the review record on the Review tab of the corresponding work item details page.
- You can view the review records in Review of the corresponding work item details page only when the work item has a general review record.
| You must have permission to check custom work items. |
| Add workloads | - Go to the work item details page and click the Workload tab.
- Click Add Workload. The Add Workload dialog box is displayed.
- Enter the workload information.
- The end date cannot be earlier than the start date.
- You can select Total or Daily for Workload.
- Work Type options include backend development, frontend development, UI design, replacement leave, debugging, and general. You can also customize the value by referring to Adding a Work Type.
- Click OK.
The system automatically generates corresponding records based on the entered dates and days. The workload can be edited and deleted. | You must have permission to add person-hours for custom work items. Workloads can be edited and deleted by the creator. By default, the project administrator can edit and delete all workloads. |
| Viewing History | History displays all operation logs of users, including creation, status transition, review initiation, work item association, and workload addition. - Access the work item details page.
- Click the History tab.
- Click
or to check historical records in the ascending or descending order of operation time. - You can set search criteria to query historical records that meet the search criteria.
| You must have permission to check custom work items. |
| Tag work item | Tags can be added to work items. Once added, the tags will appear next to . - Go to the work item details page. Click
next to Tag at the top of the page, and select Create Tag. - In the Create Tag dialog box, enter Tag Name and select Tag Color.
- Click OK.
- (Optional) Display the tag. Click
next to Tag. In the displayed dialog box, select the tag to be displayed. The tag will be displayed next to . - (Optional) Hide a tag.
- Click
next to Tag. In the displayed dialog box, deselect √ to hide the tag. - Move the cursor to the tag name and click
to hide the tag. NOTE: To add or remove tags for multiple work items, select the desired work items in the list of the custom function page, click Batch Edit in the lower part of the page, and select Tag. | You must have permission to edit custom work items. |
| Add comment | - Access the work item details page.
- On the Details tab page, click the Comments text box.
- Enter a comment.
You can upload images, enter links, associate work items, and use @ to notify project members in comments. - Click Submit.
Submitted comments can be replied, edited, pinned to the top, and deleted. | You must have permission to check custom work items. |
| Historical versions | For work items with snapshots, you can view their historical versions and compare the differences between them. NOTE: For work item types preset in IPD projects, such as raw requirements, R&D requirements, tasks, and bugs, the method of view historical versions is similar to that of custom work items. Refer to the following method. - Go to the work item details page, click
in the upper right corner, and select Version History. - In the Version History dialog box, select two versions and click Compare Versions. On the Workitem Version Comparison page, view the differences between the original version and the compared version. You can click
in the upper right corner and select Hide Identical Items to view only the differences between the two versions. - Hover over a snapshot version.
is displayed. Click to delete the snapshot. NOTE: If a work item has a third-party snapshot or its child work items have third-party snapshots and the child work items cannot be separated from the current work item, the snapshot cannot be deleted. | You must have permission to check custom work items. To delete a snapshot, you must have permission to delete custom work items. |