Deleting R&D Requirements

You can delete invalid and completed R&D requirements to release the project space.

Requirements under baseline review and change review cannot be deleted.

Prerequisites

  • A project has been created.
  • R&D requirements have been created.

Procedure

  1. In the R&D requirement list, select the requirement to be deleted.

    • To delete a single requirement, click in the row where the R&D requirement to be deleted is located and select Delete. The Warning dialog box is displayed.
    • To delete one or more requirements, select the requirements to be deleted and select Delete. The Warning dialog box is displayed.

    To delete a baselined requirement, you need to go through the review process. After the review is passed, the requirement is deleted successfully.

  2. Click Delete. A message is displayed, indicating that the deletion is successful.

More Operations

Deleted requirements can be restored from Recycle Bin.

  1. On the homepage of the R&D requirement, click Recycle Bin in the upper right corner, and the Recycle Bin window is displayed.
  2. Click in the row where the R&D requirement to be restored is located. The restoration confirmation prompt is displayed.
  3. Click OK to restore the requirement.

    The restored requirement is displayed in the R&D requirement list, staying in the status before deletion.