Updated on 2023-11-28 GMT+08:00

Creating an Execution Plan

On the stack list page, click the name of the stack to go to its details page. Click Update Template/Parameter in the upper right corner to go to the page for creating an execution plan, as shown in Figure 1.

Figure 1 Page for creating an execution plan

The subsequent steps are the same as those for creating a stack, except for one difference that you need to click Create Execution Plan instead of Directly Deploy Stack.

Then, an execution plan is generated, but the stack is not directly deployed. If you create multiple execution plans, they will exist in the same stack, as shown in Figure 2.
Figure 2 Execution plan list

Locate the row that contains the generated execution plan and click Deploy in the Operation column if you want to deploy tour execution plan.

If an execution plan is no longer used, click Delete in the Operation column. Click OK in the dialog box displayed, as shown in Figure 3.
Figure 3 Deleting an execution plan