Migration Process
Figure 1 shows the process of using SMS to migrate a server.
|
Step |
Description |
|---|---|
|
Preparations |
|
|
Installing the Agent on the Source Server |
Install and start the Agent on the source server. |
|
Configuring the Target Server |
After the migration Agent is started, configure the target server on the SMS console. |
|
Starting a Full Replication |
Replicate all data from the source server to the target server. |
|
Launching a Target Server |
After the full replication is complete, start the target server and check its running status. |
|
Synchronizing Incremental Data |
Synchronize incremental data from the source server to the target server. |