Help Center> DataArts Studio> FAQs> DataArts Factory> What Should I Do If a Job Fails to Be Executed After Being Submitted for Scheduling and an Error Displayed: Depend Job [XXX] Is Not Running Or Pause?
Updated on 2022-08-03 GMT+08:00

What Should I Do If a Job Fails to Be Executed After Being Submitted for Scheduling and an Error Displayed: Depend Job [XXX] Is Not Running Or Pause?

Symptom

After a job is submitted for scheduling, the job fails to be executed and the following error is displayed "depend job [XXX] is not running or pause".

Cause Analysis

The upstream dependency job is not in the running state.

Solutions

Check the upstream dependency jobs. If the upstream dependency jobs are not in the running state, re-schedule these jobs.