Why Is Error "Queue plans create failed. The plan xxx target cu is out of quota" Reported When I Schedule CU Changes?
Scenario
Queue plans create failed. The plan xxx target cu is out of quota is displayed when you create a scheduled scaling task.
Solution
The CU quota of the current account is insufficient. You need to apply for more quotas.
O&M Guide FAQs
- How Do I View DLI Queue Load?
- How Do I Determine Whether There Are Too Many Jobs in the Current Queue?
- How Do I Switch an Earlier-Version Spark Queue to a General-Purpose Queue?
- Why Cannot I View the Resource Running Status of DLI Queues on Cloud Eye?
- How Do I Allocate Queue Resources for Running Spark Jobs If I Have Purchased 64 CUs?
- Why Is Error "Queue plans create failed. The plan xxx target cu is out of quota" Reported When I Schedule CU Changes?
- Why Is a Timeout Exception Reported When a DLI SQL Statement Fails to Be Executed on the Default Queue?