Cost Analysis

You can view the cost breakdown trend and distribution of a certain period in multiple dimensions. Cost analysis data of the last 18 months can be queried.

Cost Breakdown Rules

Data on the page may be delayed for 24 hours.

  • For pay-per-use resources: The daily cost is calculated based on usage.
    1. If the expiration time and transaction time of a pay-per-use resource are in the same billing cycle, the cost is amortized based on the expiration date.

      Example: The expenditure time of a customer's pay-per-use resource is from 2020/06/10 23:00:00 to 2020/06/10 23:59:59, the transaction time is 2020/06/11 00:53:30, and the amount due is ¥2.

      Breakdown: Since the expiration time (2020/06/10 23:59:59) and transaction time (2020/06/11 00:53:30) are in the same billing cycle (2020/06), the ¥2 is the amortized cost of 2020/06/10.

    2. If the expiration time and transaction time of a pay-per-use resource are not in the same billing cycle, the cost is amortized based on the transaction date.

      Example: The expenditure time of a customer's pay-per-use resource is from 2020/06/30 23:00:00 to 2020/06/30 23:59:59, the transaction time is 2020/07/01 00:53:30, and the amount due is ¥2.

      Breakdown: Since the expiration time (2020/06/30 23:59:59) and transaction time (2020/07/01 00:53:30) are not in the same billing cycle, the ¥2 is the amortized cost of 2020/07/01.

  • For yearly/monthly products:

    From 2020-08-01 00:00:00, for any new expenditures, the cost is amortized based on the following rules:

    • Amortized daily cost = Order amount/Number of total valid days.
    • If the resources in an order are not enabled successfully, no cost amortization is needed.
    • If the period from the order effective time to the expiration time is less than one day, the cost does not need to be amortized and will be directly included in the cost of the expiration date.
    • Order subscription: When you unsubscribe from or downgrade an order, Amortized daily cost = Order subscription fee/Number of total valid days. If the order has already been in effect, the historical amortized amount is counted into the operation day and the amount in the future days will be amortized normally.

      Example: You subscribe to a yearly/monthly product to which five-day unconditional full refund applies for a month (from 1st to 30th) at a price of ¥60, and the amortized daily cost is ¥2. However, you unsubscribe from the product on the 3rd day for ¥60.

      Breakdown: Since the amount amortized on the 1st and 2nd days (¥2 daily) cannot be changed, the unsubscription fee can only be counted into the operation day. That is, ¥6 is returned on the 3rd day and ¥2 is returned each day from the 4th to the 30th days.

      Order Line

      Amortized on the 1st Day

      Amortized on the 2nd Day

      Amortized on the 3rd Day

      Amortized on the 4th Day

      Amortized on the 5th Day

      Amortized on the 6th Day

      ......

      Amortized on the 30th Day

      New purchase

      2

      2

      2

      2

      2

      2

      ......

      2

      5-day unconditional unsubscription

      -

      -

      -6

      -2

      -2

      -2

      ......

      -2

    • Bill adjustment: The amortized cost in the past will not change due to bill adjustments (including positive adjustments and negative adjustments). Involved historical amortized amount is counted into the operation day.

      Example: You subscribed to a yearly/monthly product for a month (from 1st to 30th) at a price of ¥60, and the amortized daily cost is ¥2. On the 3rd day, an error is found and HUAWEI CLOUD needs to return the order amount of ¥60 and charge a fee of ¥66 again.

      Breakdown: Since the amount that has been amortized on the 1st and 2nd days (¥2 daily) cannot be changed, the adjusted amount can only be counted into the operation day. That is, HUAWEI CLOUD returns an amount of ¥6 for this product and charges another fee of ¥6.6. The amortized amount in the future days remains unchanged. That is, from the 4th to the 30th days, ¥2 is returned and ¥2.2 is charged each day.

      Order Line

      Amortized on the 1st Day

      Amortized on the 2nd Day

      Amortized on the 3rd Day

      Amortized on the 4th Day

      Amortized on the 5th Day

      Amortized on the 6th Day

      ......

      Amortized on the 30th Day

      New purchase

      2

      2

      2

      2

      2

      2

      ......

      2

      Account adjustment - refund

      -

      -

      -6

      -2

      -2

      -2

      ......

      -2

      Account adjustment - payment

      -

      -

      6.6

      2.2

      2.2

      2.2

      ......

      2.2

    • Cost breakdown based on enterprise projects: Cost is amortized to the enterprise project you select when placing orders.

Cost Overview

If you log in as an enterprise master account, the overview page contains the cost data of relevant member accounts.

  1. Go to the Cost Analysis page.
  2. Click the Overview tab.
  3. Set the filter criteria to have a general view of the cost analysis.

    • Amount: Amount that a customer should pay for cloud services based on the official prices after discounts have been applied.
    • Net Amount: Equal to the amount due minus the amount of used cash coupons.

    If Linked Account is selected for an enterprise master/member account, the cost analysis data of the associated member accounts/master account will be presented.

Viewing Cost Trend and Cost Distribution

If you log in as an enterprise master account, the overview page contains the cost breakdown data of relevant member accounts. The following describes how to view the cost trend. The steps to view the cost distribution are similar.

  1. Go to the Cost Analysis page.
  2. Click the Cost Trend tab.
  3. Set the data type to view the cost trend data.

    1. By month/By day: Set the queried time period. When querying by day, you can select a maximum of 90 days.
    2. Chart: Select a line chart, column chart, or stacked column chart.
    3. Data type: Data can be filtered by product type, enterprise project, region, linked account, or billing mode.
    4. Filter: Set the filter to include or exclude certain types of data.
    5. Cost list: Costs are displayed by month based on the data type.
    6. Advanced options: Set the amount type of the expenditure data.
      • Amount: Amount that a customer should pay for cloud services based on the official prices after discounts have been applied.
      • Net Amount: Equal to the amount due minus the amount of used cash coupons.

Percentage