Billing Examples
Billing Scenarios
A customer enabled CDN on January 10, 2023 and chose to be billed by traffic. The customer added three acceleration domain names.
| Domain Name | Service Type | Service Area |
|---|---|---|
| A | Whole site acceleration | Global |
| B | File download acceleration | Chinese mainland |
| C | On-demand service acceleration | Outside the Chinese mainland |
After using CDN for a period of time, the customer found that traffic packages were more cost-effective and purchased the following two traffic packages at 09:00 (Beijing time) on April 5, 2023.
- 500 GB traffic package in the Chinese mainland valid for one month
- 1 TB traffic package outside the Chinese mainland valid for one year
The following table lists traffic and number of requests generated from April to May.
| Domain Name | Usage Before 05:00 on April 5 | Usage After 05:00 on April 5 | Usage in May |
|---|---|---|---|
| A |
|
|
|
| B | Traffic in the Chinese mainland: 40 GB | Traffic in the Chinese mainland: 200 GB | Traffic in the Chinese mainland: 230 GB |
| C | Traffic outside the Chinese mainland: 50 GB | Traffic outside the Chinese mainland: 210 GB | Traffic outside the Chinese mainland: 260 GB |
How did the customer pay for the fees of April 2023 and May 2023?
Billing Analysis
According to the CDN traffic-based billing rules, the bill of the traffic generated in an hour will be generated 4 hours later. If a traffic package is purchased, it takes effect immediately and can be used to deduct the traffic generated after the purchase. Therefore:
- Fee for traffic generated before 05:00 on April 5, 2023 was deducted from the account balance, and that for traffic generated after 05:00 on April 5, 2023 was deducted from the traffic package.
- The fee for whole site acceleration requests was deducted from the account balance.
Assume that the unit price for traffic in the Chinese mainland is ¥0.2/GB, that for traffic outside the Chinese mainland is ¥0.79/GB, and that for whole site acceleration requests is ¥0.15/10,000 requests. The fee that the customer needed to pay in April and May was calculated as follows:

The preceding prices are for reference only. The actual prices and the number of decimal places after the settlement amount are subject to the Pricing Details.
Last Article: Packages of Whole Site Acceleration Requests
Next Article: Changing the Billing Option
Did this article solve your problem?
Thank you for your score!Your feedback would help us improve the website.