Updated on 2024-10-24 GMT+08:00

Changing the AZ of a Standby DB Instance

Scenarios

You can migrate a standby DB instance to another AZ in the same region as the original AZ.

For details about regions and AZs, see Regions and AZs.

Constraints

Only when a DB instance is available and its storage is not full, you can migrate its standby instance to another AZ.

Precautions

  • Before the migration, check the resource usage of your DB instance to prevent resource overload from affecting workloads and the migration progress.
  • During the migration, if there is a large amount of data being written to the primary instance (in synchronous replication mode), the write operations may be blocked after the migration.
  • DDL operations will be suspended during the migration. To prevent service interruption, perform the migration during off-peak hours.
  • After the migration, check your workloads and verify data.
  • The migration duration is in direct proportion to the instance data volume.

Procedure

  1. Log in to the management console.
  2. Click in the upper left corner and select a region.
  3. Click in the upper left corner of the page and choose Databases > Relational Database Service.
  4. On the Instances page, locate the target DB instance and choose More > Migrate Standby DB Instance in the Operation column.
  5. On the displayed page, select a target AZ and click Submit.
  6. Check the DB instance status on the Instances page.

    • During the migration process, the DB instance status is Migrating standby DB instance. You can view the progress on the Task Center page. For details, see Task Center.
    • In the upper right corner of the DB instance list, click to refresh the list. After the migration is complete, the DB instance status will become Available.
    • On the Overview page, find AZ and check the AZ hosting the standby DB instance.