Help Center/ ModelArts/ Resource Management/ Elastic Cluster/ Modifying the Expiration Policy
Updated on 2024-04-30 GMT+08:00

Modifying the Expiration Policy

Description

ModelArts allows you to change the expiration policy of a yearly/monthly resource pool to pay-per-use or non-renewal after expiration.

Constraints

The target dedicated resource pool must be running.

Procedure

  1. Log in to the ModelArts console. In the navigation pane, choose Dedicated Resource Pools > Elastic Cluster.
  2. In the resource pool list, choose More > Change Billing Mode in the Operation column of the target resource pool.
  3. In the dialog box that appears, click OK. You will see the Renewals page of the billing center.
  4. Modify the expiration policy.
    • If auto-renewal has not been enabled for the target resource pool, click the Manual Renewals tab, and choose More > Change to Pay-per-Use After Expiration or More > Cancel Renewal in the Operation column of the target resource pool.
    • If auto-renewal has been enabled for the target resource pool, click the Auto Renewals tab, and choose More > Cancel Renewal in the Operation column of the target resource pool.