Creating a CR for Baselined Requirements
The figure below shows the process.
| Process | Description |
|---|---|
| Select a baselined R&D requirement, click Change at the bottom of the list, or go to the details page of the baseline R&D requirement and edit the fields marked with | |
| Review experts complete the CR. | |
| The decision-maker completes decision-making on the CR. | |
| Step 4: Requirement Field Values Changed Automatically upon Approval | The corresponding fields are changed automatically based on the CR conclusion. If the review fails, the change fails. |
This practice involves the following project roles, as shown in Table 2.
| Member | Role | Responsibility |
|---|---|---|
| Sarah | Project creator (product owner) | Creates a project and sets up a team. |
| Chris | Product manager | Serves as the decision-maker of the CR. |
| Maggie | Developer | Initiates the CR. |
| Frank | System engineer | Serves as a review expert of the CR. |
| Billy | System engineer | Serves as a review expert of the CR. |
| Susan | System engineer | Serves as a review expert of the CR. |
| Mike | System engineer | Serves as a review expert of the CR. |
Step 1: Trigger a CR of Baselined Requirements
To facilitate project management, configure the Priority field of R&D requirements (IR, SR, and AR) as a baseline lock field on the Fields tab under Settings > Work Item > Work Item Management. Maggie wants to change the priority of baselined requirements from Medium to High. Maggie adds these R&D requirements to the CR request to adjust their priority. Alternatively, Maggie can change the Priority of each requirement to initiate a change.
- Go to the Smart Watch project and choose . The R&D requirement list page is displayed.
- Select the baseline requirements to be changed and click Change on the operation bar in the lower part of the page, as shown in Figure 2. Alternatively, edit the Priority field of each requirement, as shown in Figure 3.
On the R&D requirement details page, a dialog box is displayed, indicating that a change review is required. Click OK. The page for creating a CR is displayed. The R&D requirements to be changed are automatically added to the list of the review.
- Enter the review information by referring to Table 3.
- Click Submit. A CR is created successfully.
- Check the new CR on the review list page. Figure 4 Review list

Step 2: (Review Experts) Complete Review
After the CR request is submitted, the review experts Billy, Frank, Susan, and Mike receive a to-do notification. Review experts access the review details page through the notification card and review the objects.
If the proportion of review experts whose review comments are Approve or Reject reaches the threshold set in , the review phase of this change object ends.
After the review phase of all change objects ends, all change objects under the CR are automatically transitioned to the decision-making phase.
If the review result of a change object is Rejected, the decision-making result will be automatically set to Rejected.
- Access the service homepage and click To-do Center in the upper right corner, or go to the smart watch project and choose . On the Change Review page, select Pending review to check the CRs that need to be reviewed. Figure 5 List of CRs to be reviewed

- Click the CR title to go to the CR details page. Click
in the Operation column of each review object. The Expert Review dialog box is displayed. Alternatively, select the review objects to be reviewed and click Batch Review.Figure 6 Change review details
- After filling in the information, click OK. The review is in the To be decided state.
Table 4 Expert review parameters Parameter
Description
Example Value
Result
Select a value as required. When Transfer to others is selected, the Review Expert selection box is displayed and you must set this parameter.
Approve
Comments
This parameter is mandatory when Result is set to Approve or Reject.
Approve
Expert Comments
If multiple review experts participate in the review, their review comments will be displayed here.
--
Figure 7 Expert review page
Step 3: (Decision-Maker) Complete Decision-Making
After all review experts complete the review, the decision-maker Chris will receive a to-do notification. Chris will then go to the project to handle the review.
- Access the service homepage and click To-do Center in the upper right corner, or go to the smart watch project and choose Review > Change Review. On the Change Review page, select Pending decision-making to view the CRs that require your decision. Figure 8 Pending decision-making

- Click the title of a CR to go to the CR details page. Click
in the Operation column of each review object. The corresponding dialog box is displayed. Alternatively, select the review objects to be decided and click Batch Decision-Making in the upper right corner.Figure 9 Decision-making details of the CR
- After the parameters are set according to Table 5, click OK. The CR status is Completed.
Table 5 Decision-making information of the decision-maker Parameter
Description
Example Value
Result
Select a value as required. When Transfer to others is selected, the Reviewer selection box is displayed and you must set this parameter.
Approve
Comments
This parameter is mandatory when Result is set to Approve or Reject.
Approve
Review Result
This parameter indicates the final result of the review.
Passed
Expert Comments
The review results and comments of review experts are displayed here.
--
Figure 10 Decision-making page
Step 4: Requirement Field Values Changed Automatically upon Approval
After the decision-making process of all change objects is complete, the CR status changes to Completed, indicating that the review is completed. Maggie, the review creator, goes to the project after receiving a notification.
- Access the service homepage and click Messages in the upper right corner, or go to the smart watch project and choose Review > Change Review. On the Change Review page, select I created to view the created CRs and their review result in the Status column. Figure 11 CR list page

- Click . On the R&D requirement list page, the Priority field of the R&D requirement added to the CR is High. The R&D requirement change process is complete. Figure 12 R&D requirement list page after the change

What is your overall rating for this page?
Thank you very much for your feedback. We will continue working to improve the documentation.See the reply and handling status in My Cloud VOC.
For any further questions, feel free to contact us through the chatbot.
Chatbot