Bug Status Transition Process

The entire lifecycle of a defect has five states: Analyzing, Fixing, Testing, Accepting, and Closed. Figure 1 shows the complete status transition process.

Figure 1 Bug status transition flowchart

Table 1 describes operations in each state.

Table 1 Operation description

Status

Description

--

Creating bugs

By default, the bug proposer is the person who finds the bug.

Analyzing

After the bug is submitted, the state changes to Analyzing.

The current owner analyzes the bug as follows:

  • If the analysis result shows that the bug is not a problem, click Fixing not required to transfer the bug to the proposer.
  • If the description is incorrect, click Return To to transfer the bug to the current owner for modification.

After the analysis is complete, click Submit to Fix.

Fixing

After the bug is analyzed, the state changes to Fixing.

The current owner fixes the bug based on the problem.

Testing

After the bug is fixed, the state changes to Testing.

The current test owner verifies whether the problem is fixed based on the rectification result. If the result does not meet the expectation, the test owner can return it for fixing or analysis.

Accepting

After the bug is tested, the state changes to Accepting.

The current acceptance owner tracks the result of the acceptance test.

Closed

After the acceptance is passed, the state changes to Closed.

A closed bug can be activated. After a bug being activated, its state will change to Analyzing.