Help Center/ AI DataLake/ User Guide/ Creating an AI DataLake Compute Resource Pool/ Adjusting the Capacity of a Compute Resource Pool
Updated on 2026-11-06 GMT+08:00

Adjusting the Capacity of a Compute Resource Pool

As service workloads increase, the capacity of existing compute resource pools may not meet the growing demand for computing power. To ensure stable service operations, administrators need to dynamically adjust the size of the compute resource pool through elastic scaling to handle peak and off-peak traffic.

Notes and Constraints

  • If a compute resource pool contains multiple resource types (CPUs, GPUs, and NPUs), only one resource type can be adjusted during a single scaling task. If multiple resource types need to be adjusted, repeat the scaling procedure for each type.
  • Scale-out and scale-in operations can be performed only on a resource pool in the Available state.
  • The time required for scale-out and scale-in to take effect depends on the instance specifications and quantity, and cannot be predetermined.
  • Before performing a scale-in, check whether running jobs are complete. The system prioritizes job execution. If a job does not complete within 30 minutes, the system will perform a forced scale-in. Consider the risk of long-running job failures before proceeding.

Scaling a Compute Resource Pool

  1. Log in to the AI DataLake console.
  2. In the left navigation pane, choose Resource Management > Compute Resource Pools.
  3. On the Compute Resource Pools page, locate the target resource pool and click Scale in the Operation column.
  4. Select the resource type, flavor, and target quantity, and click Next.

    Figure 1 Resource pool scaling

  5. Confirm the resource flavor and quantity, and click OK.

    After the task is submitted, the resource pool enters the Scaling out or Scaling in state. Wait until the resource pool scaling is complete.

    After the resource scaling is complete, the resource pool status automatically changes to Available, indicating that the capacity adjustment is complete and the new compute resources are ready for use.