WEEK
Application Scenarios
This algorithm applies when you want to shard data by day in a week. One table shard for one day is recommended.
Instructions
- The sharding key must be DATE, DATETIME, or TIMESTAMP.
- This algorithm can be used only for table sharding, instead of database sharding.
Data Routing
Use the day number of a week in the sharding key value to find the remainder. This remainder determines which table shard your data is routed to and serves as the name suffix of each table shard.
For example, if the sharding key value is 2019-01-15, the calculation of the table shard is: Day number in a week mod Table shards, that is, 3 mod 7 = 3.
Calculation Method
Condition |
Calculation Method |
Example |
---|---|---|
None |
Table routing result = Table sharding key value % Table shards |
Sharding key value: 2019-01-15 Table shard: 3 mod 7= 3 |
Syntax for Creating Tables
create table test_week_tb ( id int, name varchar(30) DEFAULT NULL, create_time datetime DEFAULT NULL, primary key(id) ) ENGINE=InnoDB DEFAULT CHARSET=utf8 dbpartition by HASH(name) tbpartition by WEEK(create_time) tbpartitions 7;
Precautions
Table shards in each database shard cannot exceed 7 because there are 7 days in a week.