How Will My Resource Packages with the Same Application Scenarios Be Used?
If you have resource packages with the same application scenarios, whichever package expires first will be applied first.
Example: A customer has the following two resource packages, which have the same application scenarios:
Resource package 1: A yearly resource package that took effect on October 10, 2019 and can be reset every month.
Resource package 2: A monthly resource package that took effect on October 12, 2019.
When to use:
- From October 10, 2019: Usage is first deducted from package 1 (that is, the package with the earliest expiration within the current reset cycle). Once package 1 is exhausted, package 2 is used.
- From October 12, 2019: Since the quota of package 1 (for the period from October 10, 2019 to November 10, 2019) is used up, usage is first deducted from package 2. After package 2 is fully consumed, any remaining usage is then deducted from package 1's next cycle (November 10, 2019 to December 10, 2019).